SŽDC Continues with Intense Preparations for Polabí HSL

At the end of September, the contract on geodetic bearing of the high-speed line Praha-Běchovice – Poříčany (HSL Polabí) was published in the Register of Contracts. The supplier of works for a price of almost CZK 10 million will be the company GEFOS. Geodesists will be working in the field up to the end of the year; they will hand in results of their work next March. Geodetic documents will speed up considerably the elaboration of documentation for a territorial decision.

In connection with preparation of the public tender Elaborating documentation for a new high-speed line (HSL) Praha-Běchovice – Poříčany territorial proceedings, a preliminary market consultation took place on 30 September at the seat of Správa železniční dopravní cesty (SŽDC). The railway infrastructure manager is interested in the tender’s ordering terms corresponding to the needs of the first high-speed line section implementation in the Czech Republic as much as possible.

Representatives of 11 designing companies from Czechia, Germany and France took part in the consultation. SŽDC informed potential suppliers on main items of the order and the model of the considered bids’ evaluation which will be based on applying the Best Value Approach/Best Value Procurement (BVA/BVP) method. This method has as objective to ensure a widest application of the suppliers’ expertise and to provide ordering entities with a possibility to distinguish the suppliers’ experience and quality.

Polabí HSL construction should be launched in 2025 as Phase I of the high-speed line Prague – Brno. SŽDC is aware of the extent of this intent in preparation; that is why it considers necessary to acquire support of the wide public by informing it regularly on the HSL construction preparation.

 

Soubory ke stažení

press release to download.pdf (108.0 kB) pdf